novinka 3In less than two months Arridere will make a complete fit out of Lidl office space in their new premises situated in the City West B1 office building in Prague district of Stodůlky. The work includes a new layout of plasterboard and glass partitions, open space, kitchenette, meeting room, restrooms, server room, etc. The change of layout entails modification of terminal elements of various technologies (air conditioning, cooling, fan coil units (FCUs), sprinkler system and lighting) as well as new weak current and partly heavy current installations. This project worth almost 8.5 million Czech korunas is handled mainly at night in order not to disturb the life of the office building and its occupants.

Delivery period: May 23 to July 10, 2016
Volume of works: approximately 8.4 mil Czech korunas